Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 125 Topic 13 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 125 Topic 13 Discussion

CAPM Exam Topic 13 Question 125 Discussion:
Question #: 125
Topic #: 13

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000


A.

1


B.

0.4


C.

0.5


D.

0.8


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.