PMI Certified Associate in Project Management (CAPM) CAPM Question # 166 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 166 Topic 17 Discussion

CAPM Exam Topic 17 Question 166 Discussion:
Question #: 166
Topic #: 17

Which of the following are processes associated with Project Cost Management?


A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs


B.

Develop Budget, Determine Budget, Determine Risks, Control Costs


C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs


D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.