New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 161 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 161 Topic 17 Discussion

CAPM Exam Topic 17 Question 161 Discussion:
Question #: 161
Topic #: 17

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?


A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.


B.

Share the project management plan with the team members again to bring them up to speed on the requirements.


C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.


D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.