PMI Certified Associate in Project Management (CAPM) CAPM Question # 161 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 161 Topic 17 Discussion

CAPM Exam Topic 17 Question 161 Discussion:
Question #: 161
Topic #: 17

When is a project finished?


A.

After verbal acceptance of the customer or sponsor


B.

After lessons learned have been documented in contract closure


C.

When the project objectives have been met


D.

After resources have been released


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.