PMI Certified Associate in Project Management (CAPM) CAPM Question # 161 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 161 Topic 17 Discussion

CAPM Exam Topic 17 Question 161 Discussion:
Question #: 161
Topic #: 17

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?


A.

Identify Stakeholders


B.

Plan Stakeholder Engagement


C.

Manage Stakeholder Engagement


D.

Monitor Slakeholder Engagement


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.