PMI Certified Associate in Project Management (CAPM) CAPM Question # 169 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 169 Topic 17 Discussion

CAPM Exam Topic 17 Question 169 Discussion:
Question #: 169
Topic #: 17

Which action should the project manager take after the team finishes executing the scope?


A.

Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.


B.

Accept all the deliverables and deliver them to the customer for final acceptance.


C.

Conduct a joint session with the customer, change the deliverables, and then request approval.


D.

Check that all change requests were implemented and release deliverables to the customer.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.