New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 169 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 169 Topic 17 Discussion

CAPM Exam Topic 17 Question 169 Discussion:
Question #: 169
Topic #: 17

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?


A.

Adaptive


B.

Hybrid


C.

Extreme


D.

Traditional


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.