PMI Certified Associate in Project Management (CAPM) CAPM Question # 87 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 87 Topic 9 Discussion

CAPM Exam Topic 9 Question 87 Discussion:
Question #: 87
Topic #: 9

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?


A.

Resource availability


B.

Infrastructure


C.

Academic research


D.

Corporate knowledge base


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.