Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 87 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 87 Topic 9 Discussion

CAPM Exam Topic 9 Question 87 Discussion:
Question #: 87
Topic #: 9

An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?


A.

Informal conversation


B.

Face-to-face meeting


C.

Short email update


D.

Written report


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.