PMI Certified Associate in Project Management (CAPM) CAPM Question # 196 Topic 20 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 196 Topic 20 Discussion

CAPM Exam Topic 20 Question 196 Discussion:
Question #: 196
Topic #: 20

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?


A.

Strong


B.

Weak


C.

Managed


D.

Balanced


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.