CAPM Exam Topic 20 Question 196 Discussion:
Question #: 196
Topic #: 20

A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?


A.

Inspection


B.

Prototyping


C.

Decision making


D.

Brainstorming