CAPM Exam Topic 20 Question 195 Discussion:
Question #: 195
Topic #: 20

Which tool or technique is used in the Perform Integrated Change Control process?


A.

Decomposition


B.

Modeling techniques


C.

Resource optimization


D.

Meetings