New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 154 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 154 Topic 16 Discussion

CAPM Exam Topic 16 Question 154 Discussion:
Question #: 154
Topic #: 16

Activity cost estimates are quantitative assessments of the probable costs required to:


A.

Create WBS.


B.

complete project work.


C.

calculate costs.


D.

Develop Project Management Plan.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.