Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 34 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 34 Topic 4 Discussion

CAPM Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

Which grid shows which resources are tied to work packages?


A.

Work breakdown structure (WBS)


B.

Responsibility assignment matrix (RAM)


C.

Project assignment chart


D.

Personnel assignment matrix


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.