PMI Certified Associate in Project Management (CAPM) CAPM Question # 21 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 21 Topic 3 Discussion

CAPM Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

As the project progresses, which of the following is routinely collected from the project activities?


A.

Communication management activities


B.

Change requests


C.

Configuration verification and audit


D.

Work performance information


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.