Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 83 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 83 Topic 9 Discussion

CAPM Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?


A.

Earned value (EV) / actual cost (AC)


B.

Estimate at completion (EAC) - AC


C.

Budget at completion (BAC) / cost performance index (CPI)


D.

EV - planned value (PV)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.