New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 83 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 83 Topic 9 Discussion

CAPM Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?


A.

-12


B.

1.15


C.

38


D.

12


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.