PMI Certified Associate in Project Management (CAPM) CAPM Question # 83 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 83 Topic 9 Discussion

CAPM Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

What does the creation of a project management plan accomplish?


A.

Defines the basis of all project work and how it will be performed


B.

Acknowledges the existence of a project and defines its high-level information


C.

Authorizes the project manager to apply organizational resources to project activities


D.

Provides the project manager with organizational standards, policies, processes, and procedures


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.