PMI Certified Associate in Project Management (CAPM) CAPM Question # 35 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 35 Topic 4 Discussion

CAPM Exam Topic 4 Question 35 Discussion:
Question #: 35
Topic #: 4

What causes replanning of the project scope?


A.

Project document updates


B.

Project scope statement changes


C.

Variance analysis


D.

Change requests


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.