CAPM Exam Topic 20 Question 197 Discussion:
Question #: 197
Topic #: 20

The following chart contains information about the tasks in a project.

CAPM Question 197

Based on the chart, what is the cost performance index (CPI) for Task 2?


A.

0.8


B.

1


C.

1.25


D.

1.8