PMI Certified Associate in Project Management (CAPM) CAPM Question # 203 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 203 Topic 21 Discussion

CAPM Exam Topic 21 Question 203 Discussion:
Question #: 203
Topic #: 21

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:


A.

adaptive


B.

reflexive


C.

predictive


D.

iterative


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.