Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 203 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 203 Topic 21 Discussion

CAPM Exam Topic 21 Question 203 Discussion:
Question #: 203
Topic #: 21

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?


A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.


B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.


C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.


D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.