New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 203 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 203 Topic 21 Discussion

CAPM Exam Topic 21 Question 203 Discussion:
Question #: 203
Topic #: 21

In an organization with a projectized organizational structure, who controls the project budget?


A.

Functional manager


B.

Project manager


C.

Program manager


D.

Project management office


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.