Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 202 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 202 Topic 21 Discussion

CAPM Exam Topic 21 Question 202 Discussion:
Question #: 202
Topic #: 21

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?


A.

Earned Schedule + Actual Time


B.

Actual Time - Earned Schedule


C.

Planned Value - Earned Value


D.

Earned Value - Planned Value


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.