A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?
According to the PMBOK® Guide, specifically the Monitor and Control Project Work process and Earned Value Management (EVM), the Schedule Variance (SV) is a quantitative measure used to determine if a project is ahead of, behind, or on its baseline schedule.
The Formula: The standard formula for calculating Schedule Variance is:
$$SV = EV - PV$$
(Where $EV$ is Earned Value and $PV$ is Planned Value).
The Components:
Earned Value ($EV$): The measure of work actually performed expressed in terms of the budget authorized for that work.
Planned Value ($PV$): The authorized budget assigned to scheduled work.
Interpreting the Result:
Positive SV ($ > 0$): The project is ahead of schedule because the value of the work performed is greater than the value of the work planned.
Negative SV ($ < 0$): The project is behind schedule because the value of work performed is less than what was planned.
Zero SV ($= 0$): The project is exactly on schedule.
Critical Path Context: While $SV$ can be calculated for any task, applying it to tasks on the critical path is vital because any negative variance there directly impacts the project ' s overall completion date.
Analysis of other options:
Option A and B: These involve Earned Schedule (ES) and Actual Time (AT). While Earned Schedule is a valid theory for measuring time-based variance, the standard formula for $SV$ in the PMBOK® Guide is based on $EV$ and $PV$. Furthermore, the formula for time-based variance is $ES - AT$, not the variations shown in A or B.
Option C: This is the inverse of the correct formula ($PV - EV$). Using this would result in a positive number when the project is behind schedule, which contradicts standard Earned Value logic where positive always equals " good. "
Per PMI standards, the most common and accepted way to communicate project performance relative to the schedule baseline is by calculating Earned Value minus Planned Value.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit