Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 6 out of 8 pages
Viewing questions 251-300 out of questions
Questions # 251:

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart


B.

Glossary of common terminology


C.

Organizational process assets


D.

Enterprise environmental factors


Expert Solution
Questions # 252:

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

Options:

A.

-9


B.

37


C.

9


D.

322


Expert Solution
Questions # 253:

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning


B.

Fast tracking


C.

Critical chain method


D.

Rolling wave planning


Expert Solution
Questions # 254:

When paying a consultation fee to a technical expert, what type of contract is often used ' ?

Options:

A.

Time and materials (TandM)


B.

Cost plus incentive fee (CPIF)


C.

Fixed price incentive fee (FPIF)


D.

Cost plus award fee (CPAF)


Expert Solution
Questions # 255:

What document gathers all of the lessons learned at the end of a phase or project

Options:

A.

Lessons learned register


B.

Lessons learned list


C.

Lessons learned project asset


D.

Lessons learned repository


Expert Solution
Questions # 256:

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control


B.

Quality Metrics


C.

Perform Quality Assurance


D.

Plan Quality


Expert Solution
Questions # 257:

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers


B.

Functional managers only


C.

Project managers only


D.

Technical managers and project managers


Expert Solution
Questions # 258:

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment


B.

Facilitation techniques and meetings


C.

Expert judgment and analytical techniques


D.

Performance reviews and meetings


Expert Solution
Questions # 259:

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports


B.

Issue log


C.

Lessons learned documentation


D.

Work performance information


Expert Solution
Questions # 260:

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.


B.

Published estimating data.


C.

Resource calendars.


D.

Resource breakdown structure (RBS).


Expert Solution
Questions # 261:

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.

What should the project manager do to address this issue?

Options:

A.

Apply emotional intelligence (El) skills, such as active listening, to understand the team ' s issues.


B.

Instruct the team members to self-organize and resolve any outstanding issues.


C.

Ask the team members to record their concerns in the lessons learned log for future action.


D.

Encourage the team to follow the project plan that was developed with team input.


Expert Solution
Questions # 262:

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports


B.

Accepted deliverables


C.

Project management plan updates


D.

Organizational process assets


Expert Solution
Questions # 263:

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)


B.

Cost Plus Incentive Fee Contract (CPIF)


C.

Firm Fixed Price Contract (FFP)


D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)


Expert Solution
Questions # 264:

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

Options:

A.

exploit


B.

avoid


C.

mitigate


D.

share


Expert Solution
Questions # 265:

Which is the communication method used in the Report Performance process?

Options:

A.

Expert judgment


B.

Project management methodology


C.

Stakeholder analysis


D.

Status review meetings


Expert Solution
Questions # 266:

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks


B.

Perform Qualitative Risk Analysis


C.

Plan Risk Management


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 267:

Which is one of the determining factors used to calculate CPI?

Options:

A.

EV


B.

SPI


C.

PV


D.

ETC


Expert Solution
Questions # 268:

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.

Installing new computers across offices


B.

Retrofitting an old building


C.

Upgrading an information system


D.

Designing a new suspension bridge


Expert Solution
Questions # 269:

Which project risk listed in the table below is most likely to occur?

Question # 269

Options:

A.

1


B.

2


C.

3


D.

4


Expert Solution
Questions # 270:

On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.

What is the advantage of using this tool?

Options:

A.

Scope creep will be prevented.


B.

Resource allocation will be kept to a minimum.


C.

Project closure will be established.


D.

Project costs will be controlled.


Expert Solution
Questions # 271:

What organizational asset can influence the Plan Risk Management process?

Options:

A.

Corporate policies and procedures for social media, ethics, and security


B.

Organizational risk policy


C.

Stakeholder register templates and instructions


D.

Organizational communication requirements


Expert Solution
Questions # 272:

Which behavior is a management trait?

Options:

A.

Asking what and why


B.

Challenging the status quo


C.

Innovating


D.

Relying on control


Expert Solution
Questions # 273:

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

Options:

A.

Activity level


B.

Deliverable level


C.

Task level


D.

Work package level


Expert Solution
Questions # 274:

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options:

A.

0.88


B.

1.12


C.

0.58


D.

1.58


Expert Solution
Questions # 275:

A procurement management plan is a subsidiary of which other type of plan?

Options:

A.

Resource plan


B.

Project management plan


C.

Cost control plan


D.

Expected monetary value plan


Expert Solution
Questions # 276:

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors


B.

Historical information and change control procedures


C.

Risk control procedures and the probability and impact matrix


D.

Resource availability and organizational culture and structure


Expert Solution
Questions # 277:

Who defines the scope of the product

Options:

A.

The client


B.

The project manager


C.

The team


D.

The program manager


Expert Solution
Questions # 278:

Which can be used to convert a verified deliverable to an accepted deliverable?

Options:

A.

Decomposition


B.

Reporting


C.

Voting


D.

Brainstorming


Expert Solution
Questions # 279:

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure


B.

Organizational breakdown structure


C.

Resource breakdown structure


D.

Bill of materials


Expert Solution
Questions # 280:

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.


B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.


C.

Determine Budget, Control Schedule, and Estimate Activity Resources.


D.

Estimate Costs, Determine Budget, and Control Costs.


Expert Solution
Questions # 281:

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Options:

A.

The influence of the stakeholders increases, the cost of changes increases.


B.

The influence of the stakeholders decreases, the cost of changes increases.


C.

The influence of the stakeholders increases, the cost of changes decreases.


D.

The influence of the stakeholders decreases, the cost of changes decreases.


Expert Solution
Questions # 282:

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.


B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.


C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.


D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.


Expert Solution
Questions # 283:

The following is a network diagram for a project.

Question # 283

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I


Expert Solution
Questions # 284:

The following chart contains information about the tasks in a project.

Question # 284

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000


B.

0


C.

1,000


D.

2,000


Expert Solution
Questions # 285:

The purpose of the Project Communications Management Knowledge Area is to:

Options:

A.

Monitor and control communications throughout the entire project life cycle.


B.

Maintain an optimal flow of information among all project participants.


C.

Develop an appropriate approach for project communications.


D.

Ensure timely and appropriate collection of project information.


Expert Solution
Questions # 286:

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

Options:

A.

Inspection


B.

Quality audits


C.

Design of experiments


D.

Root cause analysis


Expert Solution
Questions # 287:

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

Options:

A.

Strategic and business management skills


B.

Leadership skills


C.

Technical project management


D.

Organizational management


Expert Solution
Questions # 288:

A project manager is identifying the risks of a project. Which technique should the project manager use?

Options:

A.

Representations of uncertainty


B.

Prompt lists


C.

Audits


D.

Risk categorization


Expert Solution
Questions # 289:

A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.

What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?

Options:

A.

Risk management plan


B.

Cost estimate


C.

Risk register


D.

Cost management plan


Expert Solution
Questions # 290:

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work


B.

Purchase order


C.

Source selection criteria


D.

Bidder conference


Expert Solution
Questions # 291:

What is the best tool to calculate the critical path on a project?

Options:

A.

Critical chain method


B.

Graphical evaluation and review technique (GERT) diagram


C.

Gantt chart


D.

Project network diagram


Expert Solution
Questions # 292:

In project management, a temporary project can be:

Options:

A.

Completed without planning


B.

A routine business process


C.

Long in duration


D.

Ongoing to produce goods


Expert Solution
Questions # 293:

To which process is work performance information an input?

Options:

A.

Administer Procurements


B.

Direct and Manage Project Execution


C.

Create WBS


D.

Perform Qualitative Risk Analysis


Expert Solution
Questions # 294:

Match each Project Cost Management process with its appropriate keyword

Question # 294


Expert Solution
Questions # 295:

Which of the following project documents is an input to the Control Scope process?

Options:

A.

Vendor risk assessment diagram


B.

Risk register


C.

Requirements traceability matrix


D.

Area of responsibility summary


Expert Solution
Questions # 296:

Which two processes should be used to influence costs in the early stages of a project?

Options:

A.

Estimate Costs and Determine Budget


B.

Plan Cost Management and Estimate Activity Durations


C.

Control Quality and Control Costs


D.

Plan Stakeholder Engagement and Plan Communications Management


Expert Solution
Questions # 297:

The process of prioritizing risks for further analysis or action is known as:

Options:

A.

Plan Risk Management.


B.

Plan Risk Responses.


C.

Perform Qualitative Risk Analysis.


D.

Perform Quantitative Risk Analysis.


Expert Solution
Questions # 298:

Which enterprise environmental factors are considered during Estimate Costs?

Options:

A.

Market conditions and published commercial information


B.

Company structure and market conditions


C.

Commercial information and company structure


D.

Existing human resources and market conditions


Expert Solution
Questions # 299:

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50


B.

$100


C.

$125


D.

$175


Expert Solution
Questions # 300:

The process of formalizing acceptance of the completed project deliverables is known as:

Options:

A.

Validate Scope.


B.

Close Project or Phase.


C.

Control Quality.


D.

Verify Scope.


Expert Solution
Viewing page 6 out of 8 pages
Viewing questions 251-300 out of questions