Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 6 out of 8 pages
Viewing questions 251-300 out of questions
Questions # 251:

In project management, a temporary project can be:

Options:

A.

Completed without planning


B.

A routine business process


C.

Long in duration


D.

Ongoing to produce goods


Expert Solution
Questions # 252:

All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?

Options:

A.

Set up a meeting with the sponsor.


B.

Set up a go/no-go meeting.


C.

Wait for the next sprint.


D.

Deliver the product.


Expert Solution
Questions # 253:

Which provides the basic framework for managing a project?

Options:

A.

Project life cycle


B.

Work breakdown structure (WBS)


C.

Enterprise environmental factors


D.

Project initiation


Expert Solution
Questions # 254:

In a typical project, project managers spend most of their time:

Options:

A.

Estimating


B.

Scheduling


C.

Controlling


D.

Communicating


Expert Solution
Questions # 255:

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising


B.

Collaborating


C.

Smoothing


D.

Problem Solving


Expert Solution
Questions # 256:

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders


B.

Stakeholders and functional managers


C.

Project team members and consultants


D.

Project team members and stakeholders


Expert Solution
Questions # 257:

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal


B.

External


C.

Discretionary


D.

Mandatory


Expert Solution
Questions # 258:

Which tasks should a project manager accomplish in order to manage project scope correctly?

Options:

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement


B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement


C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS


D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control


Expert Solution
Questions # 259:

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Options:

A.

Project document updates


B.

Activity list


C.

Activity attributes


D.

Project calendars


Expert Solution
Questions # 260:

Which of the following describes the similarities of the process groups and project life cycle?

Options:

A.

The life cycle involves three project management process groups.


B.

Both provide a basic framework to manage the project.


C.

Each project must have a life cycle and all processes in the five process groups.


D.

The project life cycle is managed by executing the processes within the five process groups.


Expert Solution
Questions # 261:

The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?

Options:

A.

Accepted deliverables


B.

planning packages


C.

Verified deliverables


D.

Work packages


Expert Solution
Questions # 262:

" Tailoring " is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.


B.

act of creating a project team with the specialized skills required to produce a required product or service.


C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.


D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.


Expert Solution
Questions # 263:

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)

Options:

A.

High-level deliverables


B.

Phase transitions


C.

Project objectives


D.

Success criteria


E.

Cost


Expert Solution
Questions # 264:

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

Options:

A.

Organizational process assets


B.

A work breakdown structure


C.

The project management plan


D.

Enterprise environmental factors


Expert Solution
Questions # 265:

Inputs to the Plan Schedule Management process include:

Options:

A.

Organizational process assets and the project charter,


B.

Enterprise environmental factors and schedule tools.


C.

Time tables and Pareto diagrams.


D.

Activity attributes and resource calendars.


Expert Solution
Questions # 266:

Select three processes that are associated with Project Schedule Management.

Options:

A.

Define Activities


B.

Plan Resource Management


C.

Estimate Activity Durations


D.

Develop Schedule


E.

Acquire Resources


Expert Solution
Questions # 267:

Which of the following processes are part of the Project Integration Management Knowledge Area?

Options:

A.

Develop Project Management Plan, Collect Requirements, Create WBS


B.

Develop Project Management Plan, Control Scope, Develop Schedule


C.

Develop Project Charter, Define Scope, Estimate Costs


D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase


Expert Solution
Questions # 268:

How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?

Options:

A.

Adopt co-creation, sharing responsibilities with stakeholders


B.

Adopt participation of stakeholders in main meetings, listening to their opinion.


C.

Adopt social media tools, improving communication with stakeholders


D.

Adopt involvement of stakeholders in lessons learned sessions, sharing experiences with them


Expert Solution
Questions # 269:

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.


B.

statistical sampling.


C.

management responsibility,


D.

continuous improvement.


Expert Solution
Questions # 270:

Which of the following sets are inputs to the Collect Requirements process?

Options:

A.

Project charter and requirements documentation


B.

Project charter and business documents


C.

Project charter and stakeholder requirements


D.

Business documents and requirements traceability matrix


Expert Solution
Questions # 271:

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

Options:

A.

Text-oriented formal


B.

Resource management plan


C.

Organization chart


D.

Responsibility assignment matrix (RAM)


Expert Solution
Questions # 272:

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)


B.

Fixed Price Incentive Fee (FPIF)


C.

Cost Pius Award Re (CPAF)


D.

Time and Material (TandM)


Expert Solution
Questions # 273:

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

Options:

A.

Sensitivity analysis


B.

Simulation


C.

Decision tree analysis


D.

Influence diagram


Expert Solution
Questions # 274:

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing


B.

Methodology


C.

Risk categories


D.

Budgeting


Expert Solution
Questions # 275:

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram


B.

Histogram


C.

Control chart


D.

Scatter diagram


Expert Solution
Questions # 276:

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates


B.

Project management plan updates and enterprise environmental factor updates


C.

Resource calendars and project management plan updates


D.

Team performance assessments and enterprise environmental factor updates


Expert Solution
Questions # 277:

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports


B.

Issue log


C.

Lessons learned documentation


D.

Work performance information


Expert Solution
Questions # 278:

Which term describes an assessment of correctness?

Options:

A.

Accuracy


B.

Precision


C.

Grade


D.

Quality


Expert Solution
Questions # 279:

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

Options:

A.

Project


B.

Functional


C.

Program


D.

Portfolio


Expert Solution
Questions # 280:

Which of the following is an example of an organizational system that is arranged based on the job being performed?

Options:

A.

Simple


B.

Multi-divisional


C.

Functional


D.

Project-oriented


Expert Solution
Questions # 281:

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

Options:

A.

Project Schedule Management


B.

Project Scope Management


C.

Project Resource Management


D.

Project Integration Management


Expert Solution
Questions # 282:

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.


B.

risk management plan,


C.

activity list,


D.

risk register.


Expert Solution
Questions # 283:

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

Options:

A.

Monitor Communications


B.

Plan Communications Management


C.

Manage Communications


D.

Manage Stakeholder Engagement


Expert Solution
Questions # 284:

The following is a network diagram for a project.

Question # 284

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I


B.

A-B-C-F-H-I


C.

A-D-E-F-G-I


D.

A-D-E-F-H-I


Expert Solution
Questions # 285:

An intentional activity to modify a nonconforming product or product component is called:

Options:

A.

defect repair


B.

work repair


C.

corrective action


D.

preventive action


Expert Solution
Questions # 286:

A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?

Options:

A.

Add the risk to the project risk register, as the lack of solutions could impact how the product is built.


B.

Add the issue to the project issue log, as it will impact the project performance.


C.

Facilitate a brainstorming session for the team to discuss ideas to solve the problem.


D.

Meet with the project sponsor to understand their vision on how to address the problem.


Expert Solution
Questions # 287:

The activity tailoring is necessary because:

Options:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects


B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide


C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects


D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide


Expert Solution
Questions # 288:

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis


B.

Perform Quantitative Risk Analysis


C.

Control Risks


D.

Plan Risk Responses


Expert Solution
Questions # 289:

Which process uses expert judgment to manage project resources?

Options:

A.

Plan Resource Management


B.

Estimate Activity Resources


C.

Manage Team


D.

Both A and B


Expert Solution
Questions # 290:

Managing procurement relationships and monitoring contract performance are part of which process?

Options:

A.

Conduct Procurements


B.

Plan Procurements


C.

Administer Procurements


D.

Close Procurements


Expert Solution
Questions # 291:

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?

Options:

A.

Customer requirement


B.

Transition requirement


C.

Solution requirement


D.

Business requirement


Expert Solution
Questions # 292:

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier


B.

Conduct quality audits


C.

Validate Scope


D.

Validate quality requirements


Expert Solution
Questions # 293:

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03


B.

0.06


C.

0.10


D.

0.50


Expert Solution
Questions # 294:

The chart below is an example of a:

Question # 294

Options:

A.

Responsibility assignment matrix (RAM)


B.

Work breakdown structure (WBS)


C.

RACI chart


D.

Requirements traceability matrix


Expert Solution
Questions # 295:

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

Options:

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope


B.

It creates a formal record of the project and shows the organizational commitment to the project


C.

It describes how the scope will be defined, developed, monitored, controlled and validated


D.

It provides the needs of a stakeholder or stakeholder group


Expert Solution
Questions # 296:

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method


B.

Critical chain method


C.

Resource leveling


D.

Schedule network analysis


Expert Solution
Questions # 297:

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

Options:

A.

Three-point


B.

Bottom-up


C.

Parametric


D.

Analogous


Expert Solution
Questions # 298:

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars


B.

Resource leveling


C.

Resource planning


D.

Resource conflict management


Expert Solution
Questions # 299:

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests


B.

work performance information and change requests


C.

project management plan updates and work performance information


D.

issue logs and organizational process assets updates


Expert Solution
Questions # 300:

What purpose does the hierarchical locus of stakeholder communications serve?

Options:

A.

Maintains the focus on project and organizational stakeholders


B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects


C.

Sustains the focus on general communication activities using email, social media, and websites


D.

Keeps the focus on the position of the stakeholder or group with respect to the project team


Expert Solution
Viewing page 6 out of 8 pages
Viewing questions 251-300 out of questions