New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 282 Topic 29 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 282 Topic 29 Discussion

CAPM Exam Topic 29 Question 282 Discussion:
Question #: 282
Topic #: 29

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?


A.

Identify Risks


B.

Perform Qualitative Risk Analysis


C.

Plan Risk Management


D.

Perform Quantitative Risk Analysis


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.