PMI Certified Associate in Project Management (CAPM) CAPM Question # 281 Topic 29 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 281 Topic 29 Discussion

CAPM Exam Topic 29 Question 281 Discussion:
Question #: 281
Topic #: 29

In the Plan Stakeholder Management process, expert judgment is used to:


A.

Provide information needed to plan appropriate ways to engage project stakeholders.


B.

Ensure comprehensive identification and listing of new stakeholders.


C.

Analyze the information needed to develop the project scope statement.


D.

Decide the level of engagement of the stakeholders at each required stage.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.