New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 283 Topic 29 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 283 Topic 29 Discussion

CAPM Exam Topic 29 Question 283 Discussion:
Question #: 283
Topic #: 29

Which of the following is a tool and technique for Estimate Activity Durations?


A.

Parametric estimating


B.

Monte Carlo analysis


C.

Alternatives analysis


D.

Bottom-up estimating


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.