PMI Certified Associate in Project Management (CAPM) CAPM Question # 297 Topic 30 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 297 Topic 30 Discussion

CAPM Exam Topic 30 Question 297 Discussion:
Question #: 297
Topic #: 30

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?


A.

Two


B.

Four


C.

Five


D.

Twelve


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.