Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 297 Topic 30 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 297 Topic 30 Discussion

CAPM Exam Topic 30 Question 297 Discussion:
Question #: 297
Topic #: 30

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?


A.

Three-point


B.

Bottom-up


C.

Parametric


D.

Analogous


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.