PMI Certified Associate in Project Management (CAPM) CAPM Question # 296 Topic 30 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 296 Topic 30 Discussion

CAPM Exam Topic 30 Question 296 Discussion:
Question #: 296
Topic #: 30

When does the project team determine which dependencies are discretionary?


A.

Before the Define Activities process


B.

During the Define Activities process


C.

Before the Sequence Activities process


D.

During the Sequence Activities process


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.