Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 291 Topic 30 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 291 Topic 30 Discussion

CAPM Exam Topic 30 Question 291 Discussion:
Question #: 291
Topic #: 30

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?


A.

Customer requirement


B.

Transition requirement


C.

Solution requirement


D.

Business requirement


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.