PMI Certified Associate in Project Management (CAPM) CAPM Question # 294 Topic 30 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 294 Topic 30 Discussion

CAPM Exam Topic 30 Question 294 Discussion:
Question #: 294
Topic #: 30

Which input to the Plan Risk Management process provides information on high-level risks?


A.

Project charter


B.

Enterprise environmental factors


C.

Stakeholder register


D.

Organizational process assets


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.