PMI Certified Associate in Project Management (CAPM) CAPM Question # 293 Topic 30 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 293 Topic 30 Discussion

CAPM Exam Topic 30 Question 293 Discussion:
Question #: 293
Topic #: 30

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?


A.

0.8


B.

0.89


C.

1.13


D.

1.25


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.