Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 273 Topic 28 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 273 Topic 28 Discussion

CAPM Exam Topic 28 Question 273 Discussion:
Question #: 273
Topic #: 28

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?


A.

Activity level


B.

Deliverable level


C.

Task level


D.

Work package level


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.