PMI Certified Associate in Project Management (CAPM) CAPM Question # 255 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 255 Topic 26 Discussion

CAPM Exam Topic 26 Question 255 Discussion:
Question #: 255
Topic #: 26

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?


A.

Negative


B.

Zero


C.

Positive


D.

Free


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.