PMI Certified Associate in Project Management (CAPM) CAPM Question # 254 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 254 Topic 26 Discussion

CAPM Exam Topic 26 Question 254 Discussion:
Question #: 254
Topic #: 26

What are the Project Procurement Management processes?


A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements


B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements


C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements


D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.