Question #: 270
Topic #: 28

Which of the following sets are inputs to the Collect Requirements process?


A.

Project charter and requirements documentation


B.

Project charter and business documents


C.

Project charter and stakeholder requirements


D.

Business documents and requirements traceability matrix