New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 278 Topic 28 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 278 Topic 28 Discussion

CAPM Exam Topic 28 Question 278 Discussion:
Question #: 278
Topic #: 28

The project management processes presented in the PMBOK Guide® should:


A.

always be applied uniformly.


B.

be selected as appropriate by the sponsor.


C.

be selected as appropriate by the project team.


D.

be applied based on ISO guidelines.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.