Question #: 289
Topic #: 29

A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.

What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?


A.

Risk management plan


B.

Cost estimate


C.

Risk register


D.

Cost management plan