CAPM Exam Topic 39 Question 385 Discussion:
Question #: 385
Topic #: 39

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?


A.

Earned value (EV) / actual cost (AC)


B.

Estimate at completion (EAC) - AC


C.

Budget at completion (BAC) / cost performance index (CPI)


D.

EV - planned value (PV)