The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
In which type of organization does the project manager have the maximum influence
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?
Why is tailoring in a project necessary?
Which contract type is least desirable to a vendor?
A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?
Which of the following is an input to the Develop Project Charter process?
Inputs to the Plan Risk Management process include the:
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
The risk shared between the buyer and seller is determined by the:
An input to the Estimate Activity Resources process is:
Which process requires implementation of approved changes?
Which statement correctly describes the value of a business case?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
The completion of the project scope is measured against the:
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
The diagram below is an example of a:

In adaptive projects, who should approve the prioritization of the backlog?
A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?
Which is a method of prototyping that creates a functioning representation of the final finished product to the user?
A project's aim, from a business perspective, is moving an organization from one level to another to achieve a specific objective. What is the goal for a project's successful completion?
Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?
What organizational process asset (OPA) might impact a project's outcome?
What document gathers all of the lessons learned at the end of a phase or project
A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.
What should the project manager do?
The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
Which Process Group typically consumes the bulk of a project's budget?
The individual or group that provides resources and support for a project and is accountable for success is the:
Which technique is used in Perform Quantitative Risk Analysis?
An output of the Develop Project Team process is:
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Which is used to solicit proposals from prospective sellers?
Which tool is used to develop technical details within the project management plan?
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
What is a key benefit of using virtual project teams?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which is one of the major outputs of Sequence Activities?