PMI Certified Associate in Project Management (CAPM) CAPM Question # 357 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 357 Topic 36 Discussion

CAPM Exam Topic 36 Question 357 Discussion:
Question #: 357
Topic #: 36

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?


A.

Critical path method


B.

Variance analysis


C.

Schedule compression


D.

Schedule comparison bar charts


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.