PMI Certified Associate in Project Management (CAPM) CAPM Question # 358 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 358 Topic 36 Discussion

CAPM Exam Topic 36 Question 358 Discussion:
Question #: 358
Topic #: 36

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?


A.

Less time spent on defining scope early on


B.

More time spent on defining scope early on


C.

Less time spent on scope management process


D.

Project scope management is the same in all projects


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.