PMI Certified Associate in Project Management (CAPM) CAPM Question # 359 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 359 Topic 36 Discussion

CAPM Exam Topic 36 Question 359 Discussion:
Question #: 359
Topic #: 36

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?


A.

Activity dependencies


B.

Work package risks


C.

Description of work


D.

Resource estimates


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.