PMI Certified Associate in Project Management (CAPM) CAPM Question # 359 Topic 36 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 359 Topic 36 Discussion

CAPM Exam Topic 36 Question 359 Discussion:
Question #: 359
Topic #: 36

A project management office manages a number of aspects including the:


A.

Project scope, schedule, cost, and quality of the products of the work packages.


B.

Central coordination of communication management across projects.


C.

Assignment of project resources to best meet project objectives.


D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.