PMI Certified Associate in Project Management (CAPM) CAPM Question # 366 Topic 37 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 366 Topic 37 Discussion

CAPM Exam Topic 37 Question 366 Discussion:
Question #: 366
Topic #: 37

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?


A.

Acquire Resources


B.

Control Resources


C.

Manage Team


D.

Develop Team


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.