New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 366 Topic 37 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 366 Topic 37 Discussion

CAPM Exam Topic 37 Question 366 Discussion:
Question #: 366
Topic #: 37

The completion of the project scope is measured against the:


A.

requirements documentation.


B.

project scope statement.


C.

project management plan.


D.

work performance measurements.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.