Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 396 Topic 40 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 396 Topic 40 Discussion

CAPM Exam Topic 40 Question 396 Discussion:
Question #: 396
Topic #: 40

Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?


A.

Send the meeting minutes to all team members to verify that the required information is readily available.


B.

Ask the team members to provide feedback for meetings in the phase retrospective.


C.

Review the actions from the meeting with each of the project team members to ensure their understanding.


D.

Consult the communications management plan to determine the success criteria for meetings.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.