On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?


A.

Incremental life cycle


B.

Predictive life cycle


C.

Iterative life cycle


D.

Adaptive life cycle