CAPM Exam Topic 39 Question 386 Discussion:
Question #: 386
Topic #: 39

Which tool is used to develop technical details within the project management plan?


A.

Expert judgment


B.

Project management methodology


C.

Project management information system (PMIS)


D.

Project selection methods


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer: