CAPM Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?


A.

Withdraw/avoid


B.

Smooth /accommodate


C.

Collaborate/problem solve


D.

Compromise/ reconcile