The process of identifying the stakeholders' information needs is completed during:
Which tool and technique is used in Conduct Procurements?
How many Project Management Process Groups are there?
Which of the following is an input to Control Scope?
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
In which type of organizational structure are staff members grouped by specialty?
The project manager needs to review the templates in use. The templates are part of the:
Which is used to solicit proposals from prospective sellers?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Which tool or technique is used in Manage Stakeholder Expectations?
Which of the following factors is lowest at the start of the project?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Which type of risk diagram is useful for showing time ordering of events?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
What is a tool to improve team performance?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
What is the most accurate rough order of magnitude (ROM)?
The progressive detailing of the project management plan is called:
Which of the following project documents is an input to the Control Scope process?
As the project progresses, which of the following is routinely collected from the project activities?
Analogous cost estimating relies on which of the following techniques?
What is the primary benefit of meeting quality requirements?
Which technique helps to determine the risks that have the most potential impact on a project?
Which type of analysis is used as a general management technique within the Plan Procurements process?
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Which of the following documents allows the project manager to assess risks that may require near term action?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
What provides information regarding the ways people, teams, and organizational units behave?
Another name for an Ishikawa diagram is:
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
A project management office manages a number of aspects including the:
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
When does Monitor and Control Risks occur?
Which of the following statements correctly characterizes pull communication?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
The Human Resource Management processes are:
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Which of the following is TRUE about most project life cycles?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
Projects are undertaken by an organization to support the:
Cost baseline is an output of which of the following processes?