Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 3 out of 8 pages
Viewing questions 101-150 out of questions
Questions # 101:

What is a tool to improve team performance?

Options:

A.

Staffing plan


B.

External feedback


C.

Performance reports


D.

Co-location


Expert Solution
Questions # 102:

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?

Options:

A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.


B.

Accept the project delay and add the risk to the lessons learned document for the next project.


C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.


D.

Reprioritize the work based on the increased visibility of the current risks.


Expert Solution
Questions # 103:

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Options:

A.

Product analysis.


B.

Variance analysis.


C.

Document analysis,


D.

Decomposition.


Expert Solution
Questions # 104:

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

Options:

A.

plan


B.

process


C.

program


D.

portfolio


Expert Solution
Questions # 105:

What does the creation of a project management plan accomplish?

Options:

A.

Defines the basis of all project work and how it will be performed


B.

Acknowledges the existence of a project and defines its high-level information


C.

Authorizes the project manager to apply organizational resources to project activities


D.

Provides the project manager with organizational standards, policies, processes, and procedures


Expert Solution
Questions # 106:

Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

Options:

A.

Build vs. buy


B.

Expert judgment


C.

Alternatives identification


D.

Product analysis


Expert Solution
Questions # 107:

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control


B.

Quality Metrics


C.

Perform Quality Assurance


D.

Plan Quality


Expert Solution
Questions # 108:

An output of the Plan Quality Management process is:

Options:

A.

A process improvement plan,


B.

Quality control measurements.


C.

Work performance information,


D.

The project management plan.


Expert Solution
Questions # 109:

Match the life cycle type to when its requirements are defined.

Question # 109


Expert Solution
Questions # 110:

Cost baseline is an output of which of the following processes?

Options:

A.

Control Costs


B.

Determine Budget


C.

Estimate Costs


D.

Estimate Activity Resources


Expert Solution
Questions # 111:

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates


B.

Resource leveling


C.

Precedence diagramming method


D.

Bottom-up estimating


Expert Solution
Questions # 112:

Which tools or techniques will a project manager use for Develop Project Team?

Options:

A.

Negotiation


B.

Roles and responsibilities


C.

Recognition and rewards


D.

Prizing and promoting


Expert Solution
Questions # 113:

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.


B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.


C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.


D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.


Expert Solution
Questions # 114:

What tool or technique can improve a products final characteristics?

Options:

A.

Design for X (DfX)


B.

Problem solving


C.

Process analysis


D.

Risk report


Expert Solution
Questions # 115:

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement


B.

Cost performance baseline


C.

Benchmarking


D.

Cost of quality


Expert Solution
Questions # 116:

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)


B.

start-to-finish (SF)


C.

finish-to-start (FS)


D.

finish-to-finish (FF)


Expert Solution
Questions # 117:

What characteristic of servant leadership supports resource management in an agile environment?

Options:

A.

Lecturing


B.

Construing


C.

Measuring


D.

Coaching


Expert Solution
Questions # 118:

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Options:

A.

-8000


B.

-2000


C.

2000


D.

8000


Expert Solution
Questions # 119:

A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?

Options:

A.

Inspection


B.

Prototyping


C.

Decision making


D.

Brainstorming


Expert Solution
Questions # 120:

One of the objectives of a quality audit is to:

Options:

A.

highlight the need for root cause analysis.


B.

share the process documentation among stakeholders.


C.

offer assistance with non-value-added activities.


D.

identify all of the gaps or shortcomings.


Expert Solution
Questions # 121:

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition


B.

Inspection


C.

Project analysis


D.

Document analysis


Expert Solution
Questions # 122:

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams


B.

Affinity diagrams


C.

Matrix diagrams


D.

Interrelationship digraphs


Expert Solution
Questions # 123:

Match the project life cycle type with its corresponding definition.

Question # 123


Expert Solution
Questions # 124:

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

Options:

A.

Initiating


B.

Planning


C.

Executing


D.

Monitoring and Controlling


Expert Solution
Questions # 125:

In which of the Risk Management processes is the project charter used as an input?

Options:

A.

Plan Risk Responses


B.

Implement Risk Responses


C.

Plan Risk Management


D.

Perform Quantitative Risk Responses


Expert Solution
Questions # 126:

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests


B.

enterprise environmental factors


C.

the stakeholder management plan


D.

the change log


Expert Solution
Questions # 127:

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.

What should the project manager do to address this issue?

Options:

A.

Apply emotional intelligence (El) skills, such as active listening, to understand the team ' s issues.


B.

Instruct the team members to self-organize and resolve any outstanding issues.


C.

Ask the team members to record their concerns in the lessons learned log for future action.


D.

Encourage the team to follow the project plan that was developed with team input.


Expert Solution
Questions # 128:

What should be the frequency for meetings when transitioning from Scrum to Kanban?

Options:

A.

Weekly


B.

Daily


C.

When required


D.

Monthly


Expert Solution
Questions # 129:

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work


B.

Purchase order


C.

Source selection criteria


D.

Bidder conference


Expert Solution
Questions # 130:

Which task will a project manager undertake while conducting Project Resource Management?

Options:

A.

Identity the different aspects of me team to manage and control physical resources efficiently.


B.

Procure equipment, materials, facilities, and infrastructure for the project.


C.

Train the team members in project skill sets.


D.

Define the roles and responsibilities of each team member.


Expert Solution
Questions # 131:

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.


B.

Initiating,


C.

Monitoring and Controlling.


D.

Planning.


Expert Solution
Questions # 132:

In adaptive projects, who should approve the prioritization of the backlog?

Options:

A.

Project manager


B.

Project sponsor


C.

Business analyst


D.

Product owner


Expert Solution
Questions # 133:

When can we say that a project is completed?

Options:

A.

When the planned time duration is completed


B.

When the project objectives have been reached


C.

When the project manager has left the team


D.

When the project team decides to stop the work on the project


Expert Solution
Questions # 134:

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

Options:

A.

Project charter, business documents, and project management plan


B.

Agreements, scope baseline, and project management plan


C.

Project charter, business case, and project management plan


D.

Work performance data, enterprise environmental factors, and project management plan


Expert Solution
Questions # 135:

A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?

Options:

A.

Exploratory testing


B.

Integration testing


C.

User acceptance testing


D.

Day-in-the-life testing


Expert Solution
Questions # 136:

A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.

How can the manager document the business value for the Portfolio Steering Committee?

Options:

A.

Conduct a feasibility study to determine the business impact of the new product.


B.

Prepare a benefits management plan to capture target benefits and strategic alignment.


C.

Execute a market study for similar products and demonstrate a market need.


D.

Create a presentation outlining the business benefits of the new product.


Expert Solution
Questions # 137:

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs


B.

Control Costs


C.

Plan Cost Management


D.

Determine Budget


Expert Solution
Questions # 138:

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.

Which process is the project manager executing?

Options:

A.

Manage Quality


B.

Plan Quality Management


C.

Control Quality


D.

Plan Scope Management


Expert Solution
Questions # 139:

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work


B.

Resource calendars


C.

Procurement document


D.

Independent estimates


Expert Solution
Questions # 140:

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Options:

A.

Complete project phase


B.

Project life


C.

The project life cycle


D.

Project cycle


Expert Solution
Questions # 141:

Which of the following factors within a company cloud trigger the creation of a project?

Options:

A.

Need to lower production costs to remain competitive


B.

Need to submit a warranty claim for a faulty product


C.

Need to submit the monthly production report


D.

Need to define next month ' s production goals


Expert Solution
Questions # 142:

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.


B.

Sequence Activities.


C.

Define Scope.


D.

Control Schedule.


Expert Solution
Questions # 143:

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

Options:

A.

Organizational process assets


B.

Change management plan


C.

Communications management plan


D.

Resource management plan


Expert Solution
Questions # 144:

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

Options:

A.

Work performance information


B.

Bidder conferences


C.

Complexity of procurement


D.

Procurement management plan


Expert Solution
Questions # 145:

At the end of the project, what will be the value of SV?

Options:

A.

Positive


B.

Zero


C.

Negative


D.

Greater than one


Expert Solution
Questions # 146:

Which of the following is a project constraint?

Options:

A.

Twenty-five percent of staff turnover is expected.


B.

The technology to be used is cutting-edge.


C.

Project leadership may change due to a volatile political environment.


D.

The product is needed in 250 days.


Expert Solution
Questions # 147:

A graphic display of project team members and their reporting relationships is known as a:

Options:

A.

Resource calendar.


B.

Project organization chart.


C.

Resource breakdown structure (RBS).


D.

Responsibility assignment matrix (RAM).


Expert Solution
Questions # 148:

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list


B.

Project plan


C.

Activity duration estimates


D.

Project schedule


Expert Solution
Questions # 149:

Which of the following tasks is related to perform the qualitative risk analysis process?

Options:

A.

Identify the project risks and assign a probability of occurrance


B.

Perform a sensitivity analysis to determine which risk has the most potential for impacting the project


C.

Analyze the effect of identified project risks as numerical data


D.

Prioritize each project risk and assign the probability of occurrence and impact for each one


Expert Solution
Questions # 150:

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.


B.

chart.


C.

report.


D.

register.


Expert Solution
Viewing page 3 out of 8 pages
Viewing questions 101-150 out of questions