Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 3 out of 8 pages
Viewing questions 101-150 out of questions
Questions # 101:

The process of identifying the stakeholders' information needs is completed during:

Options:

A.

Plan Communications.


B.

Manage Stakeholder Expectations.


C.

Stakeholder Analysis.


D.

Identify Stakeholders.


Expert Solution
Questions # 102:

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements


B.

Expert judgment


C.

Bidder conferences


D.

Contract types


Expert Solution
Questions # 103:

How many Project Management Process Groups are there?

Options:

A.

3


B.

4


C.

5


D.

6


Expert Solution
Questions # 104:

Which of the following is an input to Control Scope?

Options:

A.

Project schedule


B.

Organizational process assets updates


C.

Project document updates


D.

Work performance information


Expert Solution
Questions # 105:

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

Options:

A.

enterprise environmental factors.


B.

organizational process assets.


C.

project management plan,


D.

project funding requirements.


Expert Solution
Questions # 106:

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional


B.

Projectized


C.

Matrix


D.

Balanced


Expert Solution
Questions # 107:

The project manager needs to review the templates in use. The templates are part of the:

Options:

A.

Enterprise environmental factors.


B.

Historical information,


C.

Organizational process assets.


D.

Corporate knowledge base.


Expert Solution
Questions # 108:

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work


B.

Resource calendars


C.

Procurement document


D.

Independent estimates


Expert Solution
Questions # 109:

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Options:

A.

Project sponsor


B.

Project manager


C.

Person responsible for project scheduling


D.

Person who is most familiar with the task


Expert Solution
Questions # 110:

Which tool or technique is used in Manage Stakeholder Expectations?

Options:

A.

Stakeholder management strategy


B.

Communication methods


C.

Issue log


D.

Change requests


Expert Solution
Questions # 111:

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes


B.

Stakeholder influences


C.

Risk


D.

Uncertainty


Expert Solution
Questions # 112:

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000


B.

US$9500


C.

US$10,000


D.

US$12,500


Expert Solution
Questions # 113:

Which type of risk diagram is useful for showing time ordering of events?

Options:

A.

Ishikawa


B.

Milestone


C.

Influence


D.

Decision tree


Expert Solution
Questions # 114:

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)


B.

Work performance information


C.

Work package


D.

Work breakdown structure (WBS)


Expert Solution
Questions # 115:

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix


B.

Work breakdown structure (WBS) dictionary


C.

Requirements management plan


D.

Requirements documentation


Expert Solution
Questions # 116:

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.


B.

Quality Control.


C.

Perform Integrated Change Control.


D.

Develop Schedule.


Expert Solution
Questions # 117:

What is a tool to improve team performance?

Options:

A.

Staffing plan


B.

External feedback


C.

Performance reports


D.

Co-location


Expert Solution
Questions # 118:

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Options:

A.

-8000


B.

-2000


C.

2000


D.

8000


Expert Solution
Questions # 119:

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.


B.

In the Planning phase, the estimate is in the range of +/- 50%.


C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.


D.

In the Closing phase, the estimate is in the range of +/- 15%.


Expert Solution
Questions # 120:

The progressive detailing of the project management plan is called:

Options:

A.

expert judgment.


B.

rolling wave planning.


C.

work performance information.


D.

specification.


Expert Solution
Questions # 121:

Which of the following project documents is an input to the Control Scope process?

Options:

A.

Vendor risk assessment diagram


B.

Risk register


C.

Requirements traceability matrix


D.

Area of responsibility summary


Expert Solution
Questions # 122:

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities


B.

Change requests


C.

Configuration verification and audit


D.

Work performance information


Expert Solution
Questions # 123:

Analogous cost estimating relies on which of the following techniques?

Options:

A.

Expert judgment


B.

Project management software


C.

Vendor bid analysis


D.

Reserve analysis


Expert Solution
Questions # 124:

What is the primary benefit of meeting quality requirements?

Options:

A.

Quality metrics


B.

Less rework


C.

Quality control measurements


D.

Benchmarking


Expert Solution
Questions # 125:

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis


B.

Expected monetary value analysis


C.

Modeling and simulation


D.

Sensitivity analysis


Expert Solution
Questions # 126:

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis


B.

Make or buy analysis


C.

Contract value analysis


D.

Cost impact analysis


Expert Solution
Questions # 127:

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

Options:

A.

There is a cost underrun.


B.

There is a cost overrun.


C.

The project may not meet the deadline.


D.

The project is 20 days behind schedule.


Expert Solution
Questions # 128:

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars


B.

Resource leveling


C.

Resource planning


D.

Resource conflict management


Expert Solution
Questions # 129:

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

Options:

A.

Brainstorming


B.

Strategies for opportunities


C.

Decision tree analysis


D.

Risk data quality assessment


Expert Solution
Questions # 130:

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix


B.

Contingency analysis report


C.

Risk urgency assessment


D.

Rolling wave plan


Expert Solution
Questions # 131:

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

Options:

A.

Cyclic


B.

Progressive


C.

Repetitive


D.

Iterative


Expert Solution
Questions # 132:

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.

Organizational chart


B.

Organizational theory


C.

Organizational structure


D.

Organizational behavior


Expert Solution
Questions # 133:

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.


B.

control chart.


C.

flowchart.


D.

histogram.


Expert Solution
Questions # 134:

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1


B.

0.4


C.

0.5


D.

0.8


Expert Solution
Questions # 135:

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.


B.

Central coordination of communication management across projects.


C.

Assignment of project resources to best meet project objectives.


D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.


Expert Solution
Questions # 136:

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning


B.

Rolling wave planning


C.

Short term planning


D.

Dependency determination


Expert Solution
Questions # 137:

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options:

A.

-700


B.

-200


C.

200


D.

500


Expert Solution
Questions # 138:

When does Monitor and Control Risks occur?

Options:

A.

At project initiation


B.

During work performance analysis


C.

Throughout the life of the project


D.

At project milestones


Expert Solution
Questions # 139:

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.


B.

It requires recipients to access communication content at their own discretion.


C.

It is the most efficient way to ensure a common understanding among all participants.


D.

It is primarily used when the volume of information to be transferred is minimal.


Expert Solution
Questions # 140:

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Options:

A.

The influence of the stakeholders increases, the cost of changes increases.


B.

The influence of the stakeholders decreases, the cost of changes increases.


C.

The influence of the stakeholders increases, the cost of changes decreases.


D.

The influence of the stakeholders decreases, the cost of changes decreases.


Expert Solution
Questions # 141:

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Options:

A.

Utilize the change control process.


B.

Crash the schedule to fix the defect.


C.

Leave the defect in and work around it.


D.

Fast-track the remaining development.


Expert Solution
Questions # 142:

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs


B.

Plan Cost Management


C.

Determine Budget


D.

Control Costs


Expert Solution
Questions # 143:

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

Options:

A.

US$158,700


B.

US$172,500


C.

US$187,500


D.

US$245,600


Expert Solution
Questions # 144:

The Human Resource Management processes are:

Options:

A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.


B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.


C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.


D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.


Expert Solution
Questions # 145:

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system


B.

Work performance information


C.

Work breakdown structure


D.

Variance analysis


Expert Solution
Questions # 146:

Which of the following is TRUE about most project life cycles?

Options:

A.

Staffing level is highest at the start.


B.

The stakeholders' influence is highest at the start.


C.

The level of uncertainty is lowest at the start.


D.

The cost of changes is highest at the start.


Expert Solution
Questions # 147:

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing


B.

Fast tracking


C.

Leads and lags adjustment


D.

Parallel task development


Expert Solution
Questions # 148:

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Options:

A.

Resource breakdown structure


B.

Staffing management plan


C.

Project organizational chart


D.

Scope management plan


Expert Solution
Questions # 149:

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.


B.

Budget process.


C.

Collective capabilities.


D.

Organizational strategy.


Expert Solution
Questions # 150:

Cost baseline is an output of which of the following processes?

Options:

A.

Control Costs


B.

Determine Budget


C.

Estimate Costs


D.

Estimate Activity Resources


Expert Solution
Viewing page 3 out of 8 pages
Viewing questions 101-150 out of questions