PMI Certified Associate in Project Management (CAPM) CAPM Question # 143 Topic 15 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 143 Topic 15 Discussion

CAPM Exam Topic 15 Question 143 Discussion:
Question #: 143
Topic #: 15

Which is an example of analogous estimating?


A.

Estimates are created by individuals or groups with specialized knowledge.


B.

Estimates are created by using information about resources of previous similar projects.


C.

Estimates are created by analyzing data.


D.

Estimates are created at the task level and aggregated upwards.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.