What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?
Tornado diagrams and influence diagrams
Detectability bubble charts and probability and impact matrix
Hierarchical charts and burndown charts
Flow charts and responsible, accountable, consult, and inform (RACI) charts