Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 142 Topic 15 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 142 Topic 15 Discussion

CAPM Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

Which of the following are outputs of Develop Project Team?


A.

Human resources plan changes and project staff assignment updates


B.

Project management plan updates and enterprise environmental factor updates


C.

Resource calendars and project management plan updates


D.

Team performance assessments and enterprise environmental factor updates


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.