Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 229 Topic 23 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 229 Topic 23 Discussion

CAPM Exam Topic 23 Question 229 Discussion:
Question #: 229
Topic #: 23

Which of the following is an input to the Direct and Manage Project Execution process?


A.

Approved change requests


B.

Approved contract documentation


C.

Work performance information


D.

Rejected change requests


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.