New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 121 Topic 13 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 121 Topic 13 Discussion

CAPM Exam Topic 13 Question 121 Discussion:
Question #: 121
Topic #: 13

After Define Activities and Sequence Activities, the next process is:


A.

Estimate Activity Resources.


B.

Estimate Activity Durations,


C.

Develop Schedule.


D.

Control Schedule.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.