PMI Certified Associate in Project Management (CAPM) CAPM Question # 121 Topic 13 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 121 Topic 13 Discussion

CAPM Exam Topic 13 Question 121 Discussion:
Question #: 121
Topic #: 13

During which process of Project Cost Management does a project manager produce the cost baseline?


A.

Estimate Costs


B.

Control Schedule


C.

Determine Budget


D.

Develop Project Charter


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.