PMI Certified Associate in Project Management (CAPM) CAPM Question # 115 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 115 Topic 12 Discussion

CAPM Exam Topic 12 Question 115 Discussion:
Question #: 115
Topic #: 12

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?


A.

Requirements traceability matrix


B.

Work breakdown structure (WBS) dictionary


C.

Requirements management plan


D.

Requirements documentation


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.