New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 131 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 131 Topic 14 Discussion

CAPM Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

Which baselines make up the performance measurement baseline?


A.

Scope baseline, cost baseline, and schedule baseline


B.

Scope baseline, project management baseline, and quality baseline


C.

Cost baseline, schedule baseline, and risk baseline


D.

Cost baseline, project management baseline, and schedule baseline


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.