PMI Certified Associate in Project Management (CAPM) CAPM Question # 131 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 131 Topic 14 Discussion

CAPM Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?


A.

Diversity background


B.

Stakeholder's relationships


C.

Technical expertise


D.

Knowledge management


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.