A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?


A.

Exploratory testing


B.

Integration testing


C.

User acceptance testing


D.

Day-in-the-life testing