Question #: 135
Topic #: 14

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?


A.

Firm-Fixed-Price (FFP)


B.

Fixed Price with Economic Price Adjustments (FP-EPA)


C.

Fixed-Price-Incentive-Fee (FPIF)


D.

Cost Plus Fixed Fee (CPFF)