PMI Certified Associate in Project Management (CAPM) CAPM Question # 141 Topic 15 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 141 Topic 15 Discussion

CAPM Exam Topic 15 Question 141 Discussion:
Question #: 141
Topic #: 15

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?


A.

Utilize the change control process.


B.

Crash the schedule to fix the defect.


C.

Leave the defect in and work around it.


D.

Fast-track the remaining development.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.