PMI Certified Associate in Project Management (CAPM) CAPM Question # 33 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 33 Topic 4 Discussion

CAPM Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:


A.

Enterprise environmental factors


B.

Work performance reports


C.

Organizational process assets


D.

Context diagrams