Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 145 Topic 15 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 145 Topic 15 Discussion

CAPM Exam Topic 15 Question 145 Discussion:
Question #: 145
Topic #: 15

Which of the following response strategies are appropriate for negative risks or threats?


A.

Share, Accept, Transfer, or Mitigate


B.

Exploit, Enhance, Share, or Accept


C.

Mitigate, Share, Avoid, or Accept


D.

Avoid, Mitigate, Transfer, or Accept


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.