Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 145 Topic 15 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 145 Topic 15 Discussion

CAPM Exam Topic 15 Question 145 Discussion:
Question #: 145
Topic #: 15

A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.

What should the project manager do?


A.

Escalate the issue to the project management office (PMO).


B.

Organize a meeting between the two managers.


C.

Ask the project team to resolve all of the open issues.


D.

Escalate to the sponsor to decide when to commence the rollout.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.